WORK ON Cell Four at the Mangrove Landfill is on track to be completed and handed over to Government by mid-year, according to an official at C.O. Williams which is carrying out the construction work.
Philip Atwell, a director and one of the leads on the $25 million project, told the SATURDAY SUN that the work, which began in May last year, should be completed by the end of June.
“There is still excavation work happening now. There’s a liner going in and select waste will be placed over the area to ensure that the liner is protected,” he said.
Atwell explained that the 15-acre landfill was being double lined to prepare for waste that would be generated from the $377 million waste-to-energy plant is to be built over a two-and-a-half year period.
Read the full story in today’s SATURDAY SUN.
On track
Previous article
Next article
Related Articles
BDF deploys Field Medical Hospital in support of Venezuela
The Barbados Defence Force’s (BDF) Field Medical Hospital will be deployed to Venezuela in the wake of a...
West Indies hit with slow over-rate fine
The West Indies won the field but lost in their pockets as they have been hit with a...
Haiti sends medical mission to assist victims in Venezuela
PORT-AU-PRINCE – The government of Haiti has dispatched a humanitarian medical mission to Venezuela to assist victims of...
We must prepare for AI, says Nicholls
The world of work is changing rapidly and Government must be prepared to adapt so that the rights...