Tuesday, January 6, 2026

Repairs continue on a failed screw lift pump at the sewage plant

Date:

Share post:

An engineering team from the Barbados Water Authority (BWA) assisted by private consultants have been working throughout the night to diagnose and commence repairing of a failed screw lift pump at the South Coast Sewage Treatment Plant (SCSTP). In the interim, an additional standby, ten-inch auxiliary pump is being commissioned to boost the influential pumping capacity.

Mechanical failure around six on Wednesday evening has been attributed to the breakdown of one of the two screw lifts in operation at the plant.

Overnight the BWA’s Wastewater Division (WWD) crews closely managed mitigating measures to keep wastewater levels low and prevent an increase in overflows in the troubled areas on the south coast. This will continue.

The BWA will update the public as the situation progresses. (PR)

Related articles

Thorne: BLP trying to steal election

The Democratic Labour Party (DLP) is accusing the Barbados Labour Party (BLP) of trying to steal the next...

Christmas Wonderland ‘a hit’

Scores of people attended The Church of Christ The King’s Christmas Wonderland on Sunday night to take in...

Wanted Man: Derick David Rudolph Crawford

Police are seeking the assistance of the public in locating Derick David Rudolph Crawford, who is wanted for...

‘Build Barbados Inc.’

Barbados is a country that needs to behave like a company so that the average Bajan can prosper.This...